Chambaria Enterprises

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ms ResidencyP52000029796Vadghar (Ct)2021Certificate Signed31 Mar 202431 Mar 2024On date
Shree Krishna KashtbhanjanPR1270002502779Kharghar2026Certificate Signed31 Dec 202930 Apr 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ms ResidencyOn date
  • Shree Krishna Kashtbhanjan+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Shree Krishna Kashtbhanjan (PR1270002502779).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology