Chalama Infraproperties Private Limited
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Dosti Planet North-Phase 2- Dosti JadeP51700018165 | Thane (M Corp.) | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Dosti Planet North - Phase 3 -Dosti OnyxP51700020162 | Thane (M Corp.) | 2019 | Certificate Signed | 30 Jun 2024 | 31 Dec 2024 | +6 months |
| Dosti Planet North- Phase 4 - Dosti OpalP51700021576 | Thane (M Corp.) | 2019 | Certificate Signed | 30 Jun 2024 | 31 Dec 2024 | +6 months |
| Dosti Planet North - Sector 3P51700034985 | Thane (M Corp.) | 2022 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Dosti Planet North - Dosti CrownP51700055335 | Thane (M Corp.) | 2024 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 6 months, for Dosti Planet North - Phase 3 -Dosti Onyx (P51700020162).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.