Chaitanya Suresh Kambli

Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ruturaj EmpireP52900006409Malwan (M Cl)2017Certificate Signed31 May 201930 Nov 2020+18 months
Ruturaj ShashwatP52900046554Malwan (M Cl)2022Certificate Signed30 Apr 202430 Apr 2024On date
Ruturaj AatmshreeP52900055057Malwan (M Cl)2024Certificate Signed10 Feb 203010 Jun 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ruturaj Empire+18 mo
  • Ruturaj ShashwatOn date
  • Ruturaj Aatmshree+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Ruturaj Empire (P52900006409).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.