Bmk Properties Private Limited

Company or firm · 4 projects · 5 MahaRERA registrations

4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kakade ResidencyP52100004336Mawal2017Certificate Signed31 Dec 201731 Dec 2017On date
Kakade- SanjeevaniP52100028898Talegaon Dabhade (M Cl)2021Certificate Signed30 Jun 202329 Jun 2024+12 months
Daulat ParkPR1260002501071Talegaon Dabhade (M Cl)2025Certificate Signed31 Dec 202730 Apr 2028+4 months
42 Park StreetPM1260002501113Varale2025Certificate Signed31 Dec 202730 Apr 2028+4 months
Daulat ParkPR1260002501344Talegaon Dabhade (M Cl)2025Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kakade ResidencyOn date
  • Kakade- Sanjeevani+12 mo
  • Daulat Park+4 mo
  • 42 Park Street+4 mo
  • Daulat Park+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Kakade- Sanjeevani (P52100028898).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology