Skip to content
Deedo home
Menu

Birari Infratech

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Parth RenaissanceP51600029998Nashik2021Not reported31 Dec 2024—On date
Avinash Co Operative Housing Society Ltd NashikP51600053499Nashik2023Not reported30 Apr 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Parth RenaissanceOn date
  • Avinash Co Operative Housing Society Ltd NashikOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology