Bhide Kulkarni Promoters And Builders

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AarohP52100030828Wadgaon Bk2021Certificate Signed31 Jan 202331 Jan 2024+12 months
JaswandiPR1260002502076Parvati2026Certificate Signed31 Jul 202830 Nov 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aaroh+12 mo
  • Jaswandi+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Aaroh (P52100030828).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology