Skip to content

Bhavya Infraventures Private Limited

Company or firm · 1 project · 3 MahaRERA registrations

Also appears as Issued to BHAVYA INFRAVENTURES PRIVATE LIMITED

1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Govind ResidencyP50500034342Nagpur (M Corp.)2022Certificate Signed31 Dec 202531 Dec 2025On date
Govind ResidencyPR1190002400042Nagpur (M Corp.)2024Certificate Signed31 Dec 202730 Apr 2028+4 months
Govind ResidencyP50500080432Nagpur (M Corp.)2025Active31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Govind ResidencyOn date
  • Govind Residency+4 mo
  • Govind ResidencyOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Govind Residency (PR1190002400042).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology