Bhavani Builders

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sadanand ResidencyP52900007520Oras Bk.2017Certificate Signed31 Mar 201930 Mar 2024+60 months
Sadanand ResidencyP52900014525Oras Bk.2017Not reported30 Mar 2024—On date
Sadanand Residency Phase IIIP52900080992Oras Bk.2025Not reported31 Mar 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sadanand Residency+60 mo
  • Sadanand ResidencyOn date
  • Sadanand Residency Phase IIIOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 60 months, for Sadanand Residency (P52900007520).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology