Bhatia Builders And Developers Pvt Ltdc

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Dahisar Sumati Chs LtdP51800003975Borivali2017Not reported31 Dec 201930 Dec 2021+24 months
Esspee TowerP51800007805Borivali2017Not reported30 Jun 202131 Jul 2027+73 months
Himat Mansion Chs LtdP51800027152Borivali2020Certificate Signed30 Jun 202730 Jun 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dahisar Sumati Chs Ltd+24 mo
  • Esspee Tower+73 mo
  • Himat Mansion Chs LtdOn date

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 73 months, for Esspee Tower (P51800007805).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology