Bharmal Builders

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gulmohar DiamondP50500045344Nagpur (M Corp.)2022Certificate Signed31 Dec 202730 Apr 2028+4 months
Monarch ResidencyPR1190002500424Godhani (Railway)2025Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gulmohar Diamond+4 mo
  • Monarch ResidencyOn date

Track record notes

  • Longest extension on record: 4 months, for Gulmohar Diamond (P50500045344).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.