Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gulmohar PlazaP50500022465Nagpur (M Corp.)2019Certificate Signed30 Dec 202430 Dec 2024On date
Gulmohar GreensP50500028868Bhilgaon2021Certificate Signed30 Jun 202630 Oct 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gulmohar PlazaOn date
  • Gulmohar Greens+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Gulmohar Greens (P50500028868).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology