Bharat Infrastructure & Engineering Private Limited
Company or firm · 4 projects · 4 MahaRERA registrations
Also appears as BHARAT REALTY VENTURE PRIVATE LIMITED
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Redevelopment of Malad Swing CHSLP51800000086 | Borivali | 2017 | Not reported | 30 Dec 2022 | — | On date |
| Redevelopment of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase IIIP51800000150 | Andheri | 2017 | Not reported | 30 Dec 2022 | — | On date |
| Redevelopment of Existing Building No. 5 known as Mahavir Nagar Tri-star CHSLP51800013803 | Borivali | 2017 | Not reported | 30 Dec 2023 | — | On date |
| Bharat Ecovistas Phase IIIP51700015290 | Thane (M Corp.) | 2018 | Not reported | 31 Mar 2022 | 10 Oct 2023 | +19 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 19 months, for Bharat Ecovistas Phase III (P51700015290).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology