Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+3 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Msr RegencyP52100004593Pune (M Corp.)2017Not reported31 Jul 201831 Dec 2018+5 months
The Jewel of PimpriP52100006848Pimpri Chinchawad (M Corp.)2017Not reported30 Dec 2021—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Msr Regency+5 mo
  • The Jewel of PimpriOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 5 months, for Msr Regency (P52100004593).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.