Bhalchandra Wadnerkar
Individual promoter · 10 projects · 10 MahaRERA registrations
Also appears as Bhalchandra Wadnerkar · Bhalchandra Vinayak Wadnerkar
10Projects10 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date5 of 10 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| NirmalP51700002522 | Dombivli | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2026 | +108 months |
| AmoghP51900002599 | Mumbai City | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| SumukhP51900004420 | Mumbai City | 2017 | Certificate Signed | 28 Feb 2018 | 28 Feb 2018 | On date |
| Jai Shree Swami SamarthP51700007190 | Dombivli | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| AjinkyataraP51900008130 | Mumbai City | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Yash PlazaP51900008150 | Ward Gnorth | 2017 | Certificate Signed | 31 Dec 2017 | 30 Dec 2018 | +12 months |
| Joshi Datta NagarP51700002586 | Dombivli | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2027 | +120 months |
| Yashoghar ChsP51700020586 | Dombivli | 2019 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Yash TrinityP51900025356 | Ward Gnorth | 2020 | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 months |
| Sai Datta KripaP51700027824 | Dombivli | 2021 | Certificate Signed | 30 Jun 2023 | 31 Dec 2027 | +54 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 10 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 120 months, for Joshi Datta Nagar (P51700002586).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology