Skip to content

Bhakti Builders

Company or firm · 7 projects · 7 MahaRERA registrations

7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
86%Kept RERA date6 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Alok HeritageP52100000289Pimpri Chinchawad (M Corp.)2017Certificate Signed31 Jul 201831 Jul 2018On date
Elysia TowersP52100027702Wakad2020Certificate Signed30 Dec 202430 Jun 2025+6 months
Pushpakunj HomesP52100031893Pimpri Chinchawad (M Corp.)2021Certificate Signed31 Dec 202331 Dec 2023On date
28 PearlsP52100046943Pimpri Chinchawad (M Corp.)2022Certificate Signed31 Dec 202431 Dec 2024On date
Bhakti ShrinidhiP52100051298Pimpri Chinchawad (M Corp.)2023Certificate Signed30 Sep 202530 Sep 2025On date
Bhakti RudvedP52100051624Pimpri Chinchawad (M Corp.)2023Certificate Signed30 Jun 202630 Jun 2026On date
Bhakti EliteP52100055213Pimpri Chinchawad (M Corp.)2024Certificate Signed30 Apr 202630 Apr 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Alok HeritageOn date
  • Elysia Towers+6 mo
  • Pushpakunj HomesOn date
  • 28 PearlsOn date
  • Bhakti ShrinidhiOn date
  • Bhakti RudvedOn date
  • Bhakti EliteOn date

Track record notes

  • 6 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 6 months, for Elysia Towers (P52100027702).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology