Bhagwati Developers
Company or firm · 3 projects · 5 MahaRERA registrations
Projects35 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases2MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Bhagwati EleganzaP51700003864 | Navi Mumbai (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Bhagwati GreensP52000003952 | Kharghar | 2017 | Not reported | 31 Dec 2024 | 31 Dec 2024 | On date |
| Bhagwati ImperiaP52000004807 | Ulawe | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Bhagwati GreensP52000006596 | Kharghar | 2017 | Not reported | 31 Dec 2024 | 31 Dec 2024 | On date |
| Bhagwati GreensP52000006873 | Kharghar | 2017 | Not reported | 31 Dec 2019 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:BHAGWATI GREENS 3 (Regulatory Case No. 236 OF 2024) dated 21 June 2024. · Bhagwati Greens · P52000003952 · 21 Jun 2024
- Regulatory orderRegulatory order: PROJECT NAME:BHAGWATI GREENS 2 (Regulatory Case No. 235 OF 2024) dated 21 June 2024. · Bhagwati Greens · P52000006596 · 21 Jun 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology