Bhagvati Infra

Company or firm · 5 projects · 6 MahaRERA registrations

5Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aura City D11,D12P52100003048Shikrapur2017Certificate Signed31 Aug 201831 Aug 2018On date
Aura City D1,D2P52100003069Shikrapur2017Certificate Signed31 Aug 201831 Aug 2018On date
Aura City D5,D6P52100003585Shikrapur2017Certificate Signed31 Oct 201831 Oct 2018On date
Aura City D3,D4P52100004141Shikrapur2017Certificate Signed31 Oct 201831 Oct 2018On date
Aura Sai KrishnanganP52100005017Koregaon Bhima (Ct)2017Certificate Signed31 Dec 202730 Apr 2028+4 months
Aura Sai KrishnanganP52100009487Koregaon Bhima (Ct)2017Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aura City D11,D12On date
  • Aura City D1,D2On date
  • Aura City D5,D6On date
  • Aura City D3,D4On date
  • Aura Sai Krishnangan+4 mo
  • Aura Sai Krishnangan+4 mo

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Aura Sai Krishnangan (P52100005017).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology