Bagad Properties
Company or firm · 5 projects · 5 MahaRERA registrations · 1 reported completed
5Projects5 RERA registrations
1Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Natures Bliss, Phase- IP51600007701 | Nashik (M Corp.) | 2017 | Certificate Signed | 30 Jan 2021 | 30 Jul 2022 | +18 months |
| Natures Pride - Phase IP51600009561 | Nashik (M Corp.) | 2017 | Completed | 20 Jun 2018 | — | On date |
| Natures Pride Phase 2P51600022281 | Nashik (M Corp.) | 2019 | Certificate Signed | 10 Dec 2023 | 20 May 2025 | +17 months |
| Iconic Business Center DwarkaP51600031959 | Nashik Shiwar | 2021 | Certificate Signed | 25 Oct 2029 | 25 Feb 2030 | +4 months |
| The ReservePM1220002502157 | Nashik | 2026 | Certificate Signed | 25 Oct 2032 | 25 Feb 2033 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 18 months, for Natures Bliss, Phase- I (P51600007701).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology