Skip to content

Avs Realtors

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+15 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ashathlaxmi Co-Operative Housing Society LimitedP51900012933Mumbai City2017Certificate Signed11 Nov 202028 Feb 2022+15 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ashathlaxmi Co-Operative Housing Society Limited+15 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 15 months, for Ashathlaxmi Co-Operative Housing Society Limited (P51900012933).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology