Avani Infrastructure

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Avani GrandP52700017320Godoli (Ct)2018Certificate Signed1 Mar 202130 Sep 2023+30 months
Saee GrandP52700020075Godoli (Ct)2019Certificate Signed15 Mar 202215 Mar 2022On date
NeelayaP52700032202Vanvaswadi2021Certificate Signed31 Dec 202531 Dec 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Avani Grand+30 mo
  • Saee GrandOn date
  • NeelayaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Avani Grand (P52700017320).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology