Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Blue FortunaP51800010900 | Andheri | 2017 | Not reported | 30 Sep 2020 | — | On date |
| Samarth Blue MountainsP51800024146 | Borivali | 2020 | Not reported | 30 Mar 2025 | — | On date |
| Blue Fortuna Phase IIP51800026518 | Andheri | 2020 | Not reported | 30 Sep 2023 | 28 Nov 2025 | +26 months |
| Atul Life Phase IP51800055779 | Nahur | 2024 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 26 months, for Blue Fortuna Phase II (P51800026518).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology