Atul Projects India Private Limited

Company or firm · 4 projects · 4 MahaRERA registrations

Also appears as ATUL PROJECTS INDIA PVT LTD

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Blue FortunaP51800010900Andheri2017Not reported30 Sep 2020—On date
Samarth Blue MountainsP51800024146Borivali2020Not reported30 Mar 2025—On date
Blue Fortuna Phase IIP51800026518Andheri2020Not reported30 Sep 202328 Nov 2025+26 months
Atul Life Phase IP51800055779Nahur2024Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Blue FortunaOn date
  • Samarth Blue MountainsOn date
  • Blue Fortuna Phase II+26 mo
  • Atul Life Phase IOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 26 months, for Blue Fortuna Phase II (P51800026518).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology