Atul Namdeo Wandile
Individual promoter · 5 projects · 5 MahaRERA registrations · 1 reported completed
Projects55 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mahakali Nagri - 6P50400019976 | Hinganghat | 2019 | Not reported | 30 Dec 2022 | — | On date |
| Makakali Nagri - 6P50400020048 | Pimpalgaon (534386) | 2019 | Not reported | 30 Mar 2022 | — | On date |
| Mahakali Nagri-7P50400024627 | Pimpalgaon (534463) | 2020 | Completed | 30 Mar 2023 | — | On date |
| Baramati CityP50400033710 | Hinganghat | 2022 | Not reported | 31 Mar 2024 | — | On date |
| Baramati CityP50400033842 | Hinganghat | 2022 | Not reported | 31 Mar 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology