Atul Builders
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Solitaire SevenP52100006186 | Baner | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Solitaire Business Hub BanerP52100008740 | Baner | 2017 | Certificate Signed | 6 Nov 2026 | 6 Nov 2026 | On date |
| Solitaire NineP52100009238 | Baner | 2017 | Certificate Signed | 31 May 2019 | 30 Nov 2020 | +18 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Solitaire Nine (P52100009238).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: SOLITAIRE BUSINESS HUB BANER (Regulatory Case No. 309 OF 2024) dated 26 Dec 2024. · Solitaire Business Hub Baner · P52100008740 · 26 Dec 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology