Atul Builders

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Solitaire SevenP52100006186Baner2017Certificate Signed31 Dec 201831 Dec 2019+12 months
Solitaire Business Hub BanerP52100008740Baner2017Certificate Signed6 Nov 20266 Nov 2026On date
Solitaire NineP52100009238Baner2017Certificate Signed31 May 201930 Nov 2020+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Solitaire Seven+12 mo
  • Solitaire Business Hub BanerOn date
  • Solitaire Nine+18 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Solitaire Nine (P52100009238).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology