Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sky Galaxy Bldg No 1P51700054404Badlapur (M Cl)2024Not reported31 Dec 2026—On date
Sky Galaxy Bldg No 2PR1330002501232Ambarnath (R)2025Not reported30 Apr 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sky Galaxy Bldg No 1On date
  • Sky Galaxy Bldg No 2On date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology