Atharv Infra Llp
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Atharv NavasamajP51800032316 | Andheri | 2021 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| AtharvmurliP51800032937 | Andheri | 2022 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Atharv AaradhyamP51800052443 | Andheri | 2023 | Certificate Signed | 30 Apr 2028 | 30 Aug 2028 | +4 months |
| Atharv Om ChandramilanP51800054052 | Vileparle | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Atharv Aaradhyam (P51800052443).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology