Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as Ashwamedh Builders & Developers

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ashwa PlatinumP51700001143Thane (M Corp.)2017Certificate Signed31 Dec 201931 Dec 2019On date
AtlantisP51700005079Thane (M Corp.)2017Certificate Signed30 Jun 202130 Dec 2022+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ashwa PlatinumOn date
  • Atlantis+18 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Atlantis (P51700005079).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology