Ashish Waman Gole

Individual promoter · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AsawariP51700009484Badlapur (M Cl)2017Certificate Signed31 Mar 201831 Mar 2018On date
Akash GangaP51700017384Badlapur (M Cl)2018Certificate Signed30 May 202330 May 2023On date
Krupa SindhuP51700020575Badlapur (M Cl)2019Certificate Signed28 Nov 202128 Nov 2021On date
AnuradhaP51700031601Badlapur (M Cl)2021Certificate Signed1 Oct 20231 Oct 2023On date
AlankapuriP51700053040Badlapur (M Cl)2023Certificate Signed1 May 20271 Sep 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • AsawariOn date
  • Akash GangaOn date
  • Krupa SindhuOn date
  • AnuradhaOn date
  • Alankapuri+4 mo

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Alankapuri (P51700053040).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology