Arihant Vatika Realty Private Limited
Company or firm · 7 projects · 8 MahaRERA registrations
Projects78 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Arihant Anmol Phase IIP51700003112 | Badlapur (M Cl) | 2017 | Not reported | 30 Sep 2020 | 30 Mar 2022 | +18 months |
| Arihant Clan Aalishan Phase IP52000006391 | Rohinjan | 2017 | Not reported | 30 Sep 2026 | — | On date |
| Arihant Anaika Phase IIP52000014892 | Koyana Velhe | 2018 | Not reported | 30 Dec 2023 | — | On date |
| Arihant Clan Aalishan Phase IIP52000017271 | Rohinjan | 2018 | Not reported | 30 Dec 2027 | — | On date |
| Arihant AmberP52000017989 | Ghot | 2018 | Not reported | 30 Dec 2026 | — | On date |
| Arihant AnmolP51700027339 | Badlapur (M Cl) | 2020 | Not reported | 30 Jun 2026 | — | On date |
| Arihant 5 AnaikaP52000029482 | Koyana Velhe | 2021 | Not reported | 31 Dec 2026 | — | On date |
| Arihant AnmolP51700049294 | Badlapur (M Cl) | 2023 | Not reported | 30 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Arihant Anmol Phase II (P51700003112).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology