Company or firm · 3 projects · 3 MahaRERA registrations · 3 reported completed

3Projects3 RERA registrations
3Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sukruti PinnacleP49900000226Jalgaon (M Corp.)2017Completed30 Jun 2018—On date
Sukruti DreamHomesP49900019018Pimprala2018Completed30 Apr 2023—On date
Sukruti SerenityP49900032651Jalgaon (M Corp.)2022Completed31 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sukruti PinnacleOn date
  • Sukruti DreamHomesOn date
  • Sukruti SerenityOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.