Arham Constrotech Pvt Ltd

Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+35 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Raman Park - Phase - IP51600004598Yeola2017Completed31 Oct 2018—On date
Raman Park Phase - IIP51600008863Yeola2017Not reported30 Sep 202030 Jun 2026+69 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Raman Park - Phase - IOn date
  • Raman Park Phase - II+69 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 69 months, for Raman Park Phase - II (P51600008863).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology