Arham Constrotech Pvt Ltd
Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed
2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+35 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Raman Park - Phase - IP51600004598 | Yeola | 2017 | Completed | 31 Oct 2018 | — | On date |
| Raman Park Phase - IIP51600008863 | Yeola | 2017 | Not reported | 30 Sep 2020 | 30 Jun 2026 | +69 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 69 months, for Raman Park Phase - II (P51600008863).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
