Arena Orchards Private Limited
Company or firm · 4 projects · 5 MahaRERA registrations
4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kalpataru Aria - Phase AP52000047146 | Varne | 2022 | Certificate Signed | 31 Dec 2024 | 24 Mar 2025 | +3 months |
| Kalpataru AriaP52000050704 | Varne | 2023 | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Kalpataru Aria - Phase CP52000051573 | Varne | 2023 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Kalpataru Aria - Phase DP52000076850 | Varne | 2024 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Kalpataru AriaP52000080104 | Varne | 2025 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Kalpataru Aria - Phase D (P52000076850).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology