Apurva Builders And Developers
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as Apurva Builders & Developers
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| The Imperial ApartmentP51600021694 | Nashik | 2019 | Not reported | 31 Jul 2024 | — | On date |
| Sai Datta Tower BP51600048231 | Nashik (M Corp.) | 2022 | Not reported | 31 Oct 2026 | — | On date |
| Vastu AvenueP51600051304 | Nashik (M Corp.) | 2023 | Not reported | 15 Aug 2026 | — | On date |
| Vastu ShilpP51600052520 | Nashik (M Corp.) | 2023 | Not reported | 31 Dec 2028 | — | On date |
| Vastu TowerP51600077708 | Nashik (M Corp.) | 2024 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology