Apex Properties

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sara Saphire Ph - IIP51500079500Aurangabad (M Corp.)2025Certificate Signed31 Dec 203030 Apr 2031+4 months
Sara Saphire Ph - IP51500079501Aurangabad (M Corp.)2025Certificate Signed31 Dec 203030 Apr 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sara Saphire Ph - II+4 mo
  • Sara Saphire Ph - I+4 mo

Track record notes

  • Longest extension on record: 4 months, for Sara Saphire Ph - II (P51500079500).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology