Anumit Buildcon Private Limited
Company or firm · 2 projects · 3 MahaRERA registrations
Also appears as ROHAN BUILDCON
2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rohan Yuva - Build AP52100023080 | Wagholi | 2019 | Certificate Signed | 30 Apr 2027 | 30 Apr 2027 | On date |
| Rohan YuvaP52100023134 | Wagholi | 2019 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Rohan YuvaP52100023214 | Wagholi | 2019 | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology