Anshuman Builders

Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Govind VillaP50300026816Mhasala2020Completed30 Jun 2024—On date
Sai CityP50300053618Kathora Bk.2023Certificate Signed31 Mar 202631 Jul 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Govind VillaOn date
  • Sai City+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Sai City (P50300053618).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology