Anmol Infra

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Patel HeritageP99000078100Vasaivirar City (M Corp)2024Certificate Signed28 Mar 202828 Jul 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Patel Heritage+4 mo

Track record notes

  • Longest extension on record: 4 months, for Patel Heritage (P99000078100).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology