Ankur Premises Developers LLP
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| PremsagarP51800004056 | Andheri | 2017 | Not reported | 31 Dec 2025 | — | On date |
| RatnadeepP51800007115 | Andheri | 2017 | Not reported | 25 May 2022 | — | On date |
| SudeshP51800014138 | Andheri | 2017 | Not reported | 24 Feb 2021 | — | On date |
| Acharat BaugP51800034682 | Andheri | 2022 | Not reported | 1 Jul 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology