Anil Wamanrao Shinde

Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VrindavanP52100016853Bavdhan Kh.2018Certificate Signed30 Jun 202230 Jun 2022On date
PanchvatiP52100020011Pune (M Corp.)2019Certificate Signed31 Dec 201931 Dec 2019On date
AnandvanP52100023793Bavdhan Kh.2020Certificate Signed30 Dec 202330 Dec 2023On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VrindavanOn date
  • PanchvatiOn date
  • AnandvanOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology