Anil Sharad Kulkarni
Individual promoter · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kamal PrideP51600013677 | Nashik (M Corp.) | 2017 | Not reported | 15 Mar 2021 | 30 Sep 2022 | +18 months |
| Kashi Row BungalowP51600028462 | Nashik | 2021 | Not reported | 30 Oct 2021 | — | On date |
| Kamal ResidencyP51600080848 | Nashik | 2025 | Not reported | 31 Oct 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 18 months, for Kamal Pride (P51600013677).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology