Anil Sharad Kulkarni

Individual promoter · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kamal PrideP51600013677Nashik (M Corp.)2017Not reported15 Mar 202130 Sep 2022+18 months
Kashi Row BungalowP51600028462Nashik2021Not reported30 Oct 2021—On date
Kamal ResidencyP51600080848Nashik2025Not reported31 Oct 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kamal Pride+18 mo
  • Kashi Row BungalowOn date
  • Kamal ResidencyOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Kamal Pride (P51600013677).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology