Skip to content
Deedo home
Menu

Anil Satyapalsingh Panwar

Individual promoter · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Satya Kiran TowerP50500050521Nagpur (M Corp.)2023Certificate Signed31 Dec 202431 Dec 2026+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Satya Kiran Tower+24 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Satya Kiran Tower (P50500050521).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology