Anant Keshaorao Saurkar

Individual promoter · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shri NandanP50300048792Amravati (M Corp.)2023Completed31 Mar 2026—On date
Shri RhideshP50300080405Amravati (M Corp.)2025Active31 Mar 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shri NandanOn date
  • Shri RhideshOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology