Individual promoter · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shiv Rai LotusP50500008500Nagpur (M Corp.)2017Completed31 Dec 2018—On date
Shivrai HibiscusP50500018028Nagpur (M Corp.)2018Not reported28 Nov 2021—On date
Shivrai LavenderP50500028605Nagpur (M Corp.)2021Not reported30 Dec 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shiv Rai LotusOn date
  • Shivrai HibiscusOn date
  • Shivrai LavenderOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology