Ami Modispaces Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ruparel StardomP51800055521Valnai2024Not reported30 Jun 2028—On date
Ruparel ZinniaP51800079098Borivali2025Certificate Signed30 Jun 202830 Oct 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ruparel StardomOn date
  • Ruparel Zinnia+4 mo

Track record notes

  • Longest extension on record: 4 months, for Ruparel Zinnia (P51800079098).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology