Ameya Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vaishnavi HeightsP51800009328Kurla2017Not reported31 Jul 201831 Jul 2019+12 months
Priya Girish Vihar CHS LtdP51800006961Kurla2017Not reported31 Dec 2017—On date
VighnahartaP51800027740Kurla2021Not reported30 Jun 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vaishnavi Heights+12 mo
  • Priya Girish Vihar CHS LtdOn date
  • VighnahartaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Vaishnavi Heights (P51800009328).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology