Ameya Developers
Company or firm · 3 projects · 4 MahaRERA registrations
3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Panvelkar DaffodilP51700019159 | Ambarnath(M Cl) | 2019 | Certificate Signed | 30 Apr 2019 | 30 Apr 2019 | On date |
| Panvelkar DaffodilP51700021441 | Ambarnath(M Cl) | 2019 | Certificate Signed | 31 Jul 2022 | 31 Dec 2023 | +17 months |
| Panvelkar Daffodil - R2P51700033104 | Ambarnath(M Cl) | 2022 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Panvelkar Daffodils-Plot No. 11,12,13PR1330002601956 | Morivali | 2026 | Certificate Signed | 31 Dec 2031 | 31 Dec 2031 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 17 months, for Panvelkar Daffodil (P51700021441).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology