Ameya Developers

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Panvelkar DaffodilP51700019159Ambarnath(M Cl)2019Certificate Signed30 Apr 201930 Apr 2019On date
Panvelkar DaffodilP51700021441Ambarnath(M Cl)2019Certificate Signed31 Jul 202231 Dec 2023+17 months
Panvelkar Daffodil - R2P51700033104Ambarnath(M Cl)2022Certificate Signed31 Dec 202531 Dec 2025On date
Panvelkar Daffodils-Plot No. 11,12,13PR1330002601956Morivali2026Certificate Signed31 Dec 203131 Dec 2031On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Panvelkar DaffodilOn date
  • Panvelkar Daffodil+17 mo
  • Panvelkar Daffodil - R2On date
  • Panvelkar Daffodils-Plot No. 11,12,13On date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 17 months, for Panvelkar Daffodil (P51700021441).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology