Amar Realty

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Amar OrchidP51700002411Dombivli2017Not reported30 Jun 2018—On date
Amar Galaxy Phase - IP51700019634Kalyan2019Not reported30 Dec 202330 Nov 2024+11 months
Amar EleganceP51700031419Chole2021Not reported30 Sep 2026—On date
Amar Galaxy Bldg No. 2 Wing B and CP51700079679Dombivli2025Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Amar OrchidOn date
  • Amar Galaxy Phase - I+11 mo
  • Amar EleganceOn date
  • Amar Galaxy Bldg No. 2 Wing B and COn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 11 months, for Amar Galaxy Phase - I (P51700019634).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology