Alchemi Developers Private Limited
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sejal SquareP51800056052 | Malad | 2024 | Not reported | 31 Dec 2029 | — | On date |
| S-City-C1P51800079113 | Malad | 2025 | Not reported | 31 Dec 2030 | — | On date |
| S-City-R2P51800079181 | Malad | 2025 | Not reported | 31 Dec 2030 | — | On date |
| S-City-R1P51800079274 | Malad | 2025 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
