Skip to content

Al Shifa Developers

Company or firm · 1 project · 1 MahaRERA registration

Also appears as AL - SHIFA DEVELOPERS

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
H - Cube - Haji Haroon HeightsP52800031168Zadgaon Ct2021Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • H - Cube - Haji Haroon Heights+4 mo

Track record notes

  • Longest extension on record: 4 months, for H - Cube - Haji Haroon Heights (P52800031168).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology