Aksha Enterprises

Company or firm · 4 projects · 5 MahaRERA registrations

4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aksha VrundavanP52100011335Haveli2017Certificate Signed31 Dec 201831 Dec 2018On date
Aksha Vrundavan IIP52100020747Haveli2019Certificate Signed30 Dec 202329 Dec 2024+12 months
Aksha VrundavanP52100029525Pimpri Chinchawad (M Corp.)2021Certificate Signed30 Sep 202630 Jan 2027+4 months
Aksha VrundavanP52100029618Pimpri Chinchawad (M Corp.)2021Certificate Signed31 Dec 202330 Dec 2024+12 months
Aksha Vrundavan IIIP52100051549Chikhali2023Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aksha VrundavanOn date
  • Aksha Vrundavan II+12 mo
  • Aksha Vrundavan+4 mo
  • Aksha Vrundavan+12 mo
  • Aksha Vrundavan III+4 mo

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Aksha Vrundavan II (P52100020747).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology