Akash Satish Patil

Individual promoter · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ganesh JoynestP52100019869Pimpri Chinchawad (M Corp.)2019Certificate Signed30 Jun 202130 Dec 2022+18 months
Ganesh JoynestP52100022087Pimpri Chinchawad (M Corp.)2019Certificate Signed30 Dec 202430 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ganesh Joynest+18 mo
  • Ganesh JoynestOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Ganesh Joynest (P52100019869).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology